Wyoming Capitol Square Project
  • Home
  • Tours
  • Guiding principles Oversight Group Task Force Project Management Project History Budget Schedule Documents & Plans Economic Benefits FAQs
  • Project Overview Capitol Restoration Central Utility Plant Replacement Capitol Extension Herschler Remodel & Expansion Site and Landscaping
  • Past Meeting & Events Media July 10 Open House and Celebration
  • Photo Updates Blog Video Social Media

Wyoming Capitol Square Project

  • Home/
  • Tours/
  • About/
    • Guiding principles
    • Oversight Group
    • Task Force
    • Project Management
    • Project History
    • Budget
    • Schedule
    • Documents & Plans
    • Economic Benefits
    • FAQs
  • Project Components/
    • Project Overview
    • Capitol Restoration
    • Central Utility Plant Replacement
    • Capitol Extension
    • Herschler Remodel & Expansion
    • Site and Landscaping
  • News/
    • Past Meeting & Events
    • Media
    • July 10 Open House and Celebration
  • Behind-the-Scenes/
    • Photo Updates
    • Blog
    • Video
    • Social Media
05-RG1_9016.jpg

Wyoming Capitol Square Project

Oversight updates

Wyoming Capitol Square Project

  • Home/
  • Tours/
  • About/
    • Guiding principles
    • Oversight Group
    • Task Force
    • Project Management
    • Project History
    • Budget
    • Schedule
    • Documents & Plans
    • Economic Benefits
    • FAQs
  • Project Components/
    • Project Overview
    • Capitol Restoration
    • Central Utility Plant Replacement
    • Capitol Extension
    • Herschler Remodel & Expansion
    • Site and Landscaping
  • News/
    • Past Meeting & Events
    • Media
    • July 10 Open House and Celebration
  • Behind-the-Scenes/
    • Photo Updates
    • Blog
    • Video
    • Social Media
May 03, 2019

May 1, 2019 presentation to Capitol Building Restoration Oversight Group

May 03, 2019/ Guest User
May 1, 2019 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on May 1, 2019 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
May 03, 2019/ Guest User/
March 22, 2019

March 21, 2019 presentation to Capitol Building Restoration Oversight Group

March 22, 2019/ Guest User
March 21, 2019 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on March 21, 2019 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
March 22, 2019/ Guest User/
November 18, 2018

November 15, 2018 presentation to Capitol Building Restoration Oversight Group

November 18, 2018/ Guest User
November 15, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on November 15, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
November 18, 2018/ Guest User/
October 19, 2018

October 17, 2018 presentation to Capitol Building Restoration Oversight Group

October 19, 2018/ Guest User
October 17, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on October 17, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
October 19, 2018/ Guest User/
August 23, 2018

August 22, 2018 presentation to Capitol Building Restoration Oversight Group

August 23, 2018/ Guest User
August 22, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on August 22, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
August 23, 2018/ Guest User/
June 22, 2018

June 14, 2018 presentation to Capitol Building Restoration Oversight Group

June 22, 2018/ Guest User
June 14, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on June 14, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
June 22, 2018/ Guest User/
May 17, 2018

May 2, 2018 presentation to Capitol Building Restoration Oversight Group

May 17, 2018/ Guest User
May 2, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on May 2, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
May 17, 2018/ Guest User/
April 16, 2018

March 27, 2018 presentation to Capitol Building Restoration Oversight Group

April 16, 2018/ Guest User
March 27, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on March 27, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items. 

Read More
April 16, 2018/ Guest User/
February 26, 2018

Feb. 8, 2018 presentation to Capitol Building Restoration Oversight Group

February 26, 2018/ Guest User
Feb. 8, 2018 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on Feb. 8, 2018 consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items. 

Read More
February 26, 2018/ Guest User/
December 28, 2017

Dec. 20, 2017 presentation to Capitol Building Restoration Oversight Group

December 28, 2017/ Guest User
Dec. 20, 2017 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on Dec. 20 to consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items. 

Read More
December 28, 2017/ Guest User/
December 04, 2017

Nov. 13, 2017 presentation to Capitol Building Restoration Oversight Group

December 04, 2017/ Guest User
Nov. 13, 2017 presentation to Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on November 13, 2017 to consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items. 

Read More
December 04, 2017/ Guest User/
September 05, 2017

July 18, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

September 05, 2017/ Guest User
July 18, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on July 18, 2017 to consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
September 05, 2017/ Guest User/
September 05, 2017

June 20, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

September 05, 2017/ Guest User
June 20, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on June 20, 2017 to consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
September 05, 2017/ Guest User/
May 03, 2017

May 2, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

May 03, 2017/ Guest User
May 2, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on May 2, 2017 to consider issues related to Capitol design, Herschler Building design, Capitol Extension design, site design, and potential change items.

Read More
May 03, 2017/ Guest User/
April 06, 2017

April 5, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

April 06, 2017/ Guest User
April 5, 2017 presentation to the Capitol Building Rehabilitation and Restoration Oversight Group

The Capitol Building Rehabilitation and Restoration Oversight Group met on April 5, 2017 to organize for the 2017-18 biennium, discuss design issues, and consider potential change items.

Read More
April 06, 2017/ Guest User/
December 21, 2016

December 20, 2016 presentation to the Capitol Building Restoration Oversight Group

December 21, 2016/ Guest User
December 20, 2016 presentation to the Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on Dec. 20, 2016 to review program manager performance pursuant to their contract, receive an update on project status, and consider potential change items.

Read More
December 21, 2016/ Guest User/
December 12, 2016

December 6, 2016 presentation to the Capitol Building Restoration Oversight Group

December 12, 2016/ Guest User
December 6, 2016 presentation to the Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on Dec. 6, 2016 to approve discrete aspects of the Capitol Square regarding Capitol design, Herschler Building design, Capitol Extension design, and site design. 

Read More
December 12, 2016/ Guest User/
October 05, 2016

October 4, 2016 presentation to the Capitol Building Restoration Oversight Group

October 05, 2016/ Guest User
October 4, 2016 presentation to the Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on October 4, 2016 in the Jonah Business Center in Cheyenne. The purpose of the meeting was to approve the discrete aspects of the Capitol Square regarding Capitol design, Herschler Building design, Capitol Extension design, and site design.

Read More
October 05, 2016/ Guest User/
July 26, 2016

July 20, 2016 presentation to the Capitol Building Restoration Oversight Group

July 26, 2016/ Guest User
July 20, 2016 presentation to the Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met on July 20, 2016.  The purpose of the meeting was to discuss design and the Guaranteed Maximum Price for the Capitol, Herschler Building, Capitol Extension, and site.

Read More
July 26, 2016/ Guest User/
June 13, 2016

June 7, 2016 presentation to the Capitol Building Restoration Oversight Group

June 13, 2016/ Guest User
June 7, 2016 presentation to the Capitol Building Restoration Oversight Group

The Capitol Building Restoration Oversight Group met in Cheyenne on June 7, 2016 to discuss Capitol design and Herschler Building design.

Read More
June 13, 2016/ Guest User/
  • Next
  • Home/
  • Tours/
  • About/
    • Guiding principles
    • Oversight Group
    • Task Force
    • Project Management
    • Project History
    • Budget
    • Schedule
    • Documents & Plans
    • Economic Benefits
    • FAQs
  • Project Components/
    • Project Overview
    • Capitol Restoration
    • Central Utility Plant Replacement
    • Capitol Extension
    • Herschler Remodel & Expansion
    • Site and Landscaping
  • News/
    • Past Meeting & Events
    • Media
    • July 10 Open House and Celebration
  • Behind-the-Scenes/
    • Photo Updates
    • Blog
    • Video
    • Social Media

Wyoming Capitol Square Project

 
2019-0713-brochure-small-1.jpg

View the Capitol Square Tour Book.

Hours of Operation: Monday-Friday 8:00 a.m.- 5:00 p.m.

Questions about visiting call (307) 777-7881

Contact the Capitol Square Construction Project at (307) 777-7271 or email CapitolSquare@wyo.gov.